Signature Plant
Why Tour our Purpose-Built Plant
Production Capacity: Up to 600 modules per year, equivalent to about 8,000 SQFT per week
Throughput: Modules complete the in plant production sequence in under 10 business days once they hit the line.
Construction Range: From custom ranches and two-story homes to PHIUS certified senior living and student housing.
Coverage - North Carolina to Maine: Signature primarily delivers modules throughout the Northeast Corridor including states in New England and Mid-Atlantic.
Who Tours: Homebuyers, home builders, GCs, developers, lenders, and design teams looking for a true manufacturing partner.
Signature Building Systems Virtual Factory Tour
Production Facility at a Glance
Location: 1004 Springbrook Ave, Moosic, PA
Footprint: 80,000 sq. ft.
Ceiling Height: 40 ft
Purpose-built in 2001
Built for Volume: Streamlined pre-assembly stations for framing allows for seamless coordination with MEP rough-in, insulation, air sealing, finishes, and QC on the main assembly line. The purpose built modular plant is optimized for both custom one-offs and repeatable multifamily.
“PFS TECO | an NFPA Global Solutions™ Company – is proud to recognize Signature Building Systems’ Moosic, PA facility for its commitment to quality. The manufacturer consistently operates in accordance with approved quality assurance procedures, maintains an organized and efficient production environment, and meets state program requirements for code compliance.”
-Bob Gorsecki, Vice President of Manufactured Structures Division, PFS TECO
What You’ll See on the Modular Plant Tour
Line Flow & Stations: Precision jigs, automated saws and nailers, synchronized substations, standardized work instructions, and coordinated material staging.
Quality in Motion: Internal QC at every station with documented checkpoints and external third-party inspections where required.
Safety Culture: Daily focus on safe material handling, crane and equipment training, and OSHA compliance.
Delivery Readiness: How modules are sealed, prepped, and staged for transport and set.
Signature Modular Plant FAQs
How fast do modules move through the plant?
Once design approvals and long-lead procurement are complete, modules typically move through the line in about 8 business days. Start dates depend on scope and line slot availability.
What do you build?
Everything from custom capes and two-stories to multifamily buildings (student, senior, hospitality, workforce). All modular projects are fabricated to the state codes, and local codes set by the GC/developer.
What’s your annual capacity?
Up to 600 modules per year, roughly 500,000 SQFT of prefinished building area, subject to mix and complexity.
How do I schedule a tour?
Click here and use our form. Select “Plant Tour”:
Benefits of a controlled environment for construction
Quality: Repeatable assemblies, standardized inspections, and consistent factory conditions deliver higher-quality construction with tighter tolerances.
Sustainability: Indoor conditions support better building science, stronger air sealing, and more accurate insulation for improved long-term energy performance.
Waste Reduction: Controlled material handling and protection from weather reduce waste, damage, and unnecessary rework.
Efficiency: Factory sequencing, coordinated labor, and parallel site work shorten project timelines and improve overall efficiency.
Predictability: A stable production environment reduces delays, limits variability, and results in more reliable schedules and outcomes.
Delivering Custom Solutions
Signature has a wide variety of projects under its belt, from single-family homes to hotels, motels, assisted living facilities, townhouses, and retirement communities. Whatever the project, the company is able to deliver a customized solution. Using computer aided design (CAD) technology, Signature’s draftsmen work closely with the customer’s builder to create a unique design. Or, customers can simply choose from a long list of standard plans.
Signature maintains a goal of building 60 modules a month, about 50 percent of which are used in single-family homes. On average, a two story single-family home requires three to four modules, while a ranch only needs two. The largest module that the company can build measures 15’9” x 66’, but these modules can be put together in virtually any configuration onsite, allowing the team to create extremely large residential structures in addition to single family homes.
For example, Signature built an entire dorm in Syracuse, New York for State University of New York’s Environmental Sciences and Forestry School (SUNY-ESF). The team used a whopping 184 modules to build the Centennial Hall dormitory in 2010, then created an addition using 70 modules in 2014. The largest project that Signature has completed to date, the dorm has been well received on campus for its environmentally friendly construction.
Schedule your plant tour now and experience the systems, people, and process that make Signature the industry’s most reliable modular partner. Email INFO@SBSMOD.COM to schedule a tour or click the button below.